Quoting Dependencies Between Operations

When there are dependencies between operations, delays in handling, transportation, transmission or thinking time, etc. between operation steps we refer to this as lag time.

I talked previously about job cost estimating setup time.   The four areas that were spoken about where staging time, setup time, transit time and tear down time.   Each one of these 4 processes actually would add costs to an estimate.   Lag time does not add costs to an actual estimate under most circumstances.

When there are dependencies between operations, delays in handling, transportation, transmission or thinking time, etc. between operation steps we refer to this as lag time.   Lag time does not usually add costs to a operation step because there is no activity actually being performed except for taking up space on the manufacturing shop floor.   If there were large lag times you may consider putting a dollar value on the floor space but this may be overkill during the quoting and estimating process.

On the other hand lag time is a critical factor during scheduling of a job shop.   This lag time is critical in ERP/MRP systems in order to properly handle dependencies between operation steps.   The objective is to minimize the time a job is sitting idle with no work being performed.   Reducing cycle time by decreasing the queue time between manufacturing steps is a basic principle of lean manufacturing to reduce work in process inventory.

Quoting and Estimating is not an area where lag time is usually considered because there are direct costs that could be attributed.    As prepare your estimate keep in mind lag time because it will be used in scheduling the job shop.

MIE Solutions products including MIE QuoteIt and MIE Trak both can help a job shops quoting and estimating process more accurate.

http://www.mie-solutions.com/mie/index.php/MIE-QuoteIt/

http://www.mie-solutions.com/mie/

Author: MIE Solutions

David Ferguson has over 20 years of experience in the manufacturing and fabrication industry. David Ferguson has been to over 100 manufacturing companies helping and guiding them to be more efficient and cost effective. As a child in Junior High School David Ferguson found a passion for the early computer systems, which would drive much of his future work. David Ferguson created and sold his first computer program, Arrow Data Systems, which was an early CAD/CAM system for the Apple 2e Computer. In the late 1980's after seeing his father (a sheet metal manufacturer) come home many nights estimating, David Ferguson saw an opportunity to optimize his effort through computer technology. Shortly thereafter the FabriTRAK Production Control package was developed. The Quote It! estimating package was developed out of the FabriTRAK system to become one of the leading sheet metal estimating packages in the world. David Ferguson has always had a passion for developing software to make the manufacturing process simpler, faster and more efficient. Prior to founding MIE Solutions David Ferguson worked with his father at Alco Sheet Metal, METALSOFT Inc. and was a consultant at Toyota Motors Sales. David Ferguson has his Masters in Computer Science and Mathematics from California State University, Long Beach.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s